From 1943 to 1970, much of the uranium ore mined in the United
States was processed by private companies under procurement contracts
with the U.S. Atomic Energy Commission. This ore was used in national
defense research, weapons development, and the developing nuclear
industry. After fulfilling their contracts, many of the uranium
mills closed and left large quantities of waste, such as uranium
mill tailings and abandoned mill buildings, at the mill sites.
Beginning in the late 1960s and 1970s, direct gamma radiation,
radon gas, and uranium decay products at the abandoned mill sites
were determined to be potential health hazards. In 1972 concern
for the potential long-term adverse health affects from uranium
mill tailings used as fill material in construction projects in
Grand Junction, Colorado, led Congress to pass Title II of Public
Law 92-314, which authorized the Atomic Energy Commission to pay
for 75 percent of the cost of remediating such contaminated buildings.
Public concern about other abandoned uranium mill sites led to
engineering and radiological studies to identify other mill sites
in need of cleanup. As a result of these studies Congress passed
the Uranium Mill Tailings Radiation Control Act (UMTRCA) on November
8, 1978 (42 USC §7901 et seq.).
The UMTRCA directed the U.S. Department of Energy (DOE) to stabilize,
dispose of, and control, in a safe and environmentally sound manner,
uranium mill tailings at the designated inactive uranium mill
sites. To comply with the law, DOE established the Uranium Mill
Tailings Remedial Action (UMTRA) Project. Under the UMTRA Project,
DOE has been performing remedial action of the surface contamination
(including uranium mill tailings and abandoned mill buildings)
since 1983; this effort is called the UMTRA Surface Project. The
first site to be cleaned up is in Canonsburg, Pennsylvania; surface
remediation has now been completed at 18 sites and is under way
at 4 sites. The designated uranium mill sites at Belfield and
Bowman, North Dakota, will not be remediated by DOE because the
state of North Dakota has declined to provide their statutorily
required cost-sharing to remediate the sites. Although it is unlikely
that these two sites will be part of the UMTRA Ground Water Project,
discussion of the sites is still included in the programmatic
environmental impact statement (PEIS). The Surface Project is
responsible for controlling the exposure and dispersion of uranium
mill tailings and other contaminated materials by stabilizing
this material in disposal cells. However, the Surface Project
does not address the remediation of contaminated ground water
at the UMTRA Project sites. Information about the Surface Project
is summarized in Sections 3.1 and 3.2 of this PEIS.
The UMTRA Ground Water Project addresses residual ground water
contamination, if any, from the UMTRA Project processing sites.
The Ground Water Project would take measures to protect human
health and the environment by complying with EPA standards in
a cost-effective and publicly acceptable manner. The UMTRA Ground
Water Project also would address potential ground water contamination
associated with vicinity properties (properties outside the processing
site boundary contaminated with tailings) on a case-by-case basis.
The volume of tailings at a vicinity property site is just one
of the criteria for determining if the vicinity property would
be a source for ground water contamination and would fall within
the Ground Water Project. Another difference between contamination
from a processing site and a vicinity property site is that processing
sites had the potential to impact ground water due to the use
of chemicals, water discharge, and exposed saturated tailings.
In most cases, the tailings were exposed to the environment for
many years before remediation. Vicinity properties did not have
similar operating and exposure conditions which would minimize
or eliminate the potential for vicinity properties to be a source
of ground water contamination. Other factors include depth to
ground water, magnitude of source, soil and bedrock geochemistry,
ground water recharge and discharge, background water geochemistry,
climate, and condition of the vicinity property.
The UMTRCA requires that EPA promulgate standards for protecting
public health, safety, and the environment from radiological
hazardous constituents associated with the processing, possession,
transfer, and disposal of residual radioactive materials. The
UMTRCA and EPA define residual radioactive materials as tailings
and other wastes that DOE determines to be radioactive that
have resulted from uranium ores processing. These wastes may
be in the form of tailings or other materials such as demolition
debris and nonradiological hazards associated with residual
radioactive materials. EPA has interpreted this definition to
include sludges and captured contaminated water from the processing
sites (60 FR 2854).
On January 5, 1983, EPA published standards (40 CFR Part 192)
for the disposal and cleanup of residual radioactive materials.
On September 3, 1985, the Tenth Circuit Court of Appeals set
aside and remanded to EPA the ground water provisions of the
standards. EPA proposed new standards to replace remanded sections
and changed other sections of 40 CFR Part 192. These proposed
standards were published in the Federal Register on September
24, 1987 (52 FR 36000). Section 108 of the UMTRCA requires that
DOE comply with EPA's proposed standards in the absence of final
standards. The Ground Water Project was planned under the proposed
standards. On January 11, 1995, EPA published the final rule,
with which the DOE must now comply. The PEIS and the Ground
Water Project are in accordance with the final standards. The
EPA reserves the right to modify the ground water standards,
if necessary, based on changes in EPA drinking water standards.
Appendix A contains a copy of the 1983 EPA ground water compliance
standards, the 1987 proposed changes to the standards, and the
1995 final rule.
The EPA standards have three subparts that apply to the UMTRA
Project: Subpart A, Subpart B, and Subpart C.
Subpart A-Standards for residual radioactive materials
Subpart A, "Standards for the Control of Residual Radioactive
Materials From Inactive Uranium Processing Sites," addresses
control or disposal of the residual radioactive materials at
processing or disposal sites. Compliance with Subpart A is being
met under the UMTRA Surface Project. This subpart is not discussed
further.
Subpart B-Background levels, maximum concentration limits,
alternate concentration limits, monitoring, natural flushing
Subpart B, "Standards for Cleanup of Land and Buildings
Contaminated With Residual Radioactive Materials From Inactive
Uranium Processing Sites," requires conducting remedial
action at processing sites to ensure that the amounts of residual
radioactive materials and associated hazardous constituents
in ground water do not exceed any one of the following three
standards in 60 FR 2854:
- Background levels for these constituents.
- Maximum concentration limits-EPA's maximum concentration
of certain hazardous constituents for ground water protection.
Hazardous constituents with maximum concentration limits that
may be present in contaminated ground water at UMTRA Project
sites include arsenic, barium, cadmium, chromium, lead, mercury,
molybdenum, nitrate, radium, selenium, silver, and uranium.
- Alternate concentration limits-concentrations of contaminants
that may exceed the maximum concentration limits; or, limits
for those constituents without maximum concentration limits.
If DOE determines, and NRC concurs, that human health and
the environment would not be adversely affected, DOE may meet
an alternate concentration limit.
Subpart B also defines limited use ground water. Ground water
may be classified as limited use if the total dissolved solids
exceed 10,000 milligrams per liter (mg/L); there is widespread
surrounding contamination that cannot be cleaned up using treatment
methods reasonably employed in public water supply systems;
or the quantity of ground water available is less than 150 gallons
(gal) (570 liters [L]) per day.
Subpart B also has provisions that allow natural flushing as
a way to meet the EPA ground water standards. Natural flushing
means letting natural ground water processes reduce the contamination
in ground water to background levels, below the maximum concentration
limits, or to alternate concentration limits. The following
conditions must be met before natural flushing can be implemented:
- Natural flushing must allow standards (background levels,
maximum concentration limits, or alternate concentration limits)
to be met within 100 years.
- Institutional controls with a high degree of permanence
that will effectively protect public health and the environment,
and satisfy beneficial uses of ground water must be viable
and enforceable (a description of institutional controls is
provided below).
- Ground water must not be a current or projected source for
a public water system during the period of natural flushing.
A public water system is defined in 40 CFR §125.58 as
a "system for the provision to the public of piped water
for human consumption, if such system has at least fifteen
(15) service connections or regularly serves at least twenty-five
(25) individuals. This term (public water system) includes
1) any collection, treatment, storage, and distribution facilities
under the control of the operator of the system and used primarily
in connection with the system; and 2) any collection of pretreatment
storage facilities not under the control of the operator of
the system which are used primarily in connection with the
system."
Subpart B also requires that DOE monitor the ground water contamination
for compliance with Subpart B standards and define the extent
of ground water contamination so that measures can be taken,
if necessary, to protect human health and the environment.
The EPA standards specify a point of compliance for disposal
of the surface contamination but indicate that this does not
suffice for the cleanup of contaminated ground water. For the
Ground Water Project, "compliance must be achieved anywhere
contamination above the levels established by these standards
is found or projected to be found in ground water outside the
disposal area and its cover" (60 FR 2854).
Subpart C-Implementation
Subpart C, "Implementation," provides guidance for
implementing methods and procedures that will reasonably assure
the public that the provisions of Subparts A and B are satisfied.
The conditions of Subpart B should be met on a site-specific
basis, using information gathered from site characterization
and monitoring. The plan to meet the conditions of Subpart B
should be stated in the compliance strategy document or remedial
action plan. This plan should also consider future ground water
plume movement. If natural flushing is the selected compliance
strategy, Subpart C requires compliance monitoring to verify
anticipated plume movement and the associated reduction in plume
contamination. Finally, the plan should specify details of the
method to be used to meet the standards and, if necessary, the
remedial action.
Supplemental standards
Subpart C specifies eight conditions for which DOE may apply
supplemental standards to contaminated ground water. These standards
are supplemental to background levels, maximum concentration
limits, or alternate concentration limits. Supplemental standards
as cited below in 40 CFR §192.21 may be applied if any
one of the following conditions is met:
a) Remedial actions required to satisfy Subpart A or B of the
standards would pose a clear and present risk of injury to workers
or to members of the public, notwithstanding reasonable measures
to avoid or reduce risk.
b) Remedial actions to satisfy the cleanup standards for land
and ground water, notwithstanding reasonable measures to limit
damage, would directly produce health and environmental harm
that is clearly excessive compared to the health and environmental
benefits, now or in the future. A clear excess of health and
environmental harm is harm that is long-term, manifest, and
grossly disproportionate to health and environmental benefits
that may reasonably be anticipated.
c) The estimated cost of remedial action to meet the standards
at a "vicinity" site is unreasonably high relative
to the long-term benefits, and the residual radioactive materials
do not pose a clear present or future hazard. The likelihood
that buildings will be erected or that people will spend long
periods of time at such a vicinity site should be considered
in evaluating this hazard. Remedial action will generally not
be necessary where residual radioactive materials have been
placed semi-permanently in a location where minor quantities
of residual radioactive materials are involved. Examples are
residual radioactive materials under hard surface public roads
and sidewalks, around public sewer lines, or in fence post foundations.
Supplemental standards should not be applied at such sites,
however, if individuals are likely to be exposed for long periods
of time to radiation from such materials at levels above those
that would prevail under the standards.
d) The cost of a remedial action for cleanup of a building
under the standards is clearly unreasonably high relative to
the benefits. Factors that should be included in this judgment
are the anticipated period of occupancy, the incremental radiation
level that would be affected by the remedial action, the residual
useful lifetime of the building, the potential for future construction
at the site, and the applicability of less costly remedial methods
than removal of residual radioactive materials.
e) There is no known remedial action.
f) The restoration of ground water quality at any designated
processing site is technically impracticable from an engineering
perspective.
g) The ground water is not a current or potential source of
drinking water, in the absence of contamination from residual
radioactive materials, due to the following:
- the concentration of total dissolved solids is in excess
of 10,000 mg/L or,
- widespread, ambient contamination not due to activities
involving residual radioactive materials from a designated
processing site exists that cannot be cleaned up using treatment
methods reasonably employed in public water systems. Ambient
conditions caused by natural or human-induced conditions exclude
contributions from residual radioactive materials or,
- the quantity of water reasonably available for sustained
continuous use is less than 150 gal (570 L) per day. The parameters
for determining the quantity of water reasonably available
shall be determined by the DOE with the concurrence of the
NRC.
h) Radionuclides other than radium-226 and its decay products
are present in sufficient quantity and concentration to constitute
a significant radiation hazard from residual radioactive materials.
The standards that most likely would apply to the Ground Water
Project are b, e, f, and g above.
The EPA final rule states that if supplemental standards are
applied, DOE must select and perform remedial action that comes
as close to meeting the otherwise applicable standard as reasonably
achievable. Supplemental standards must also ensure that current
and projected uses of the affected ground water are preserved.
Institutional controls
Institutional controls are controls that effectively protect
public health and the environment. They typically depend on
some social order to ensure that protection is effective. On
the UMTRA Ground Water Project, institutional controls would
reduce exposure to or mitigate health risks by 1) preventing
intrusion into contaminated ground water, or 2) restricting
access to or use of contaminated ground water for unacceptable
purposes. As a last resort, institutional controls could limit
human access to the land above the contaminated ground water.
The EPA standards allow the use of institutional controls in
place of remediation only if their effectiveness can be verified
and maintained. The EPA standards permit the use of institutional
controls at sites where remediation can occur through natural
flushing of the aquifer within 100 years. However, the standards
do not limit the use of institutional controls to the sites
that can meet the standards through natural flushing. Institutional
controls may also be used to protect public health or the environment
when DOE finds them necessary and appropriate prior to commencing
active remedial action, during active remedial action, or during
implementation of other compliance strategies.
The EPA standards require that institutional controls
- have a high degree of permanence.
- protect public health and the environment.
- satisfy beneficial uses of ground water.
- are enforceable by administrative or judicial branches of
government entities.
- can be effectively maintained and verified.
An example of acceptable institutional controls cited in the
EPA standards is deed restriction that can be enforced by a
unit of government (either administratively or through judicial
processes). Another example is federal or state ownership of
land containing contaminated ground water. EPA recognizes that
a combination of controls may be needed to adequately protect
public health and safety. Measures such as signs, health advisories,
or other measures that require voluntary cooperation of private
parties can be used to complement other enforceable institutional
controls but cannot be considered as primary protective measures.
In addition, the use of an alternate water supply in conjunction
with institutional controls that would prevent human contact
with contaminated ground water would be a viable institutional
control.
Key to identifying, implementing, and enforcing institutional
controls is participation by tribal, state, and local governments.
While DOE is responsible for compliance with the EPA standards
at UMTRA sites, its authority to implement and enforce institutional
controls may be limited, particularly where tailings are disposed
of off the processing site and land is privately owned or is
owned or controlled by other public agencies. Similarly, ground
water contamination from uranium processing may have moved beyond
the processing site to areas that are not within the DOE jurisdiction.
The need for and duration of institutional controls depends
on the compliance strategy selected for a site, the type and
level of risk, and existing site conditions. As risks decrease
over time, so should the restrictiveness of institutional controls.
Contaminated plume movement might require applying the restrictions
to an extended area over time. Therefore, to ensure extended
protection of public health, the environment, and beneficial
uses the water could have satisfied, it is important that the
effectiveness of institutional controls can be verified and
modified as necessary.
Institutional controls, if any, will be selected in cooperation
with the participating private and public landowners, Indian
tribes, states, and local governments. DOE will verify that
the institutional controls are effective. Site-specific institutional
controls will not be selected and implemented without DOE and
NRC concurrence.
1.4.2 NRC licensing regulations and
program
The UMTRCA authorized DOE to care for the uranium mill tailings
disposal sites under a license issued by NRC. The UMTRCA stipulates
the NRC will promulgate regulations to ensure the permanent
disposal sites are monitored and maintained in accordance with
the general license. Regulations in 10 CFR §40.27, General
License for Custody and Long-Term Care of Residual Radioactive
Material Disposal Sites, describe the licensing mechanism for
the long-term care of each UMTRA Project disposal site, when
NRC accepts the site-specific long-term surveillance plan. Long-term
care includes surveillance and maintenance needed to protect
public health and safety.
On-site stabilization
At former processing sites where tailings are stabilized in
on-site disposal cells, contaminated ground water may require
remediation. This could occur if ground water moves from below
the disposal cell. NRC may license these disposal sites in two
steps. The first step is NRC's acceptance of the long-term care
program for all surface remedial action that includes compliance
with the EPA standards that protect the ground water from further
contamination from the tailings. In the second step, the DOE
must verify, and NRC must concur that ground water compliance
has been met in accordance with 40 CFR Part 192, Subpart B;
then the long-term surveillance plan will be appropriately amended,
signifying that the second step of the licensing process is
complete.
Off-site stabilization
For the disposal cells where the residual radioactive materials
were relocated off the processing site, NRC will license the
disposal site in one step. The processing sites themselves will
not be licensed by NRC. Compliance with EPA ground water standards
will require NRC concurrence.
1.4.3 DOE requirements
DOE Order 5400.1, General Environmental Protection Program,
established environmental protection program requirements for
DOE operations, including the UMTRA Project, for ensuring compliance
with executive orders and applicable federal, tribal, state,
and local environmental protection laws and regulations. DOE
also established requirements for the protection of the public
and workers from radiological hazards in DOE Order 5400.5, Radiation
Protection of the Public and the Environment; DOE Order 5480.11,
Radiation Protection for Occupational Workers; and 10 CFR Part
835, Occupational Radiation Protection. These and all other
applicable requirements are routinely incorporated into UMTRA
Project activities.
1.4.4 DOE Office of Environmental
Justice requirements
Executive Order 12898, Federal Action to Address Environmental
Justice in Minority Populations and Low Income Populations,
directs federal agencies to identify and address, as appropriate,
disproportionately high and adverse human health or environmental
effects of their programs, policies, and activities on minority
and low-income populations. Executive Order 12898 also directs
the EPA administrator to convene an interagency Federal Working
Group on Environmental Justice. The Working Group is directed
to provide guidance to federal agencies on criteria for identifying
disproportionately high and adverse human health or environmental
effects on minority and low-income populations. The Working
Group has not yet issued the guidance directed by Executive
Order 12898. In coordination with the Working Group, the DOE
is in the process of developing internal guidance on implementing
the Executive Order. Because both the Working Group and the
DOE are still in the process of developing guidance, the approach
taken in this analysis may depart somewhat from the guidance
that is eventually issued, but will comply with the intent of
the Executive Order.
1.4.5 Other Presidential Executive
Order requirements
Executive Order 11990, Protection of Wetlands, requires all
federal agencies to issue or amend existing procedures to ensure
wetlands protection is considered in decision-making. This requirement
is routinely incorporated into UMTRA Project activities.
Executive Order 11988, Floodplain Management, requires each
federal agency to issue or amend existing regulations and procedures
to ensure that the potential effects of any action it may take
in a floodplain are evaluated and that its planning programs
and budget requirements reflect consideration of flood hazards
and floodplain management. UMTRA Project activity planning routinely
identifies and considers the impacts of Project actions on floodplains.
1.4.6 Tribal law requirements
DOE shall follow all applicable tribal laws and regulations
in performing ground water compliance activities on Indian lands.
In the event of conflicting applications of federal, state,
and tribal law, the subject activity will be carried out pursuant
to the following order of priority in application: 1) federal,
2) tribal, and 3) state.
1.5 PROPOSED ACTION SUMMARY
This PEIS considers four approaches (also called "alternatives")
for implementing the UMTRA Ground Water Project. These alternatives
are described in Section 2.0.
The proposed action (preferred alternative) is summarized below.
The proposed action provides a consistent approach, based on
a health- and environmental risk-based framework, for implementing
the UMTRA Ground Water Project and determining appropriate ground
water compliance strategies at the UMTRA Project processing
sites. The success of the proposed action in determining these
strategies would depend on the analysis of site-specific data
to characterize the hydrogeological conditions and determine
the potential human health and environmental risks.
The following site-specific ground water compliance strategies
could be used under the proposed action:
- No remediation.
- Natural flushing.
- Active ground water remediation.
These strategies could be used individually or in combination
to meet the standards. For example, active ground water remediation
methods could be used in conjunction with natural flushing.
The proposed action is flexible because it provides a framework
for the Ground Water Project decision-making process if new
ground water cleanup methods become available. The proposed
action considers ground water compliance in a step-by-step approach,
beginning with the no remediation strategy and ending with more
complex, active ground water cleanup strategies. When a site
baseline risk assessment for ground water contamination and
a site observational work plan indicate the no remediation strategy
would be protective of human health and the environment, a more
expensive strategy involving active cleanup methods would not
be necessary. The proposed action would tailor ground water
compliance strategies for each site, based on the likelihood
that they would result in conditions that are protective of
human health and the environment. A more detailed description
of the proposed action appears in Section
2.1.
1.6 PUBLIC PARTICIPATION
An important component of the PEIS is the participation by
government agencies, organizations, the public, and other interested
parties in determining the scope and content of this PEIS and
reviewing and commenting on the draft and final PEIS. Throughout
the UMTRA Ground Water Project, the DOE will provide opportunities
for productive, ongoing discussions with the public and local,
state, tribal, and federal officials as part of DOE's daily
activities.
Regulations that implement NEPA (in 40 CFR §1501.7) stipulate
there must be an early, open, and continuing public participation
process for determining the scope of the issues that will be
addressed and for identifying significant issues related to
the proposed action. This process is called scoping. The UMTRA
Ground Water Project PEIS scoping process began with the preparation
of a Notice of Intent, published in the Federal Register on
November 18, 1992 (57 FR 54374). Dates, locations, and times
for public scoping meetings were published in the Federal Register
on February 8, 1993 (58 FR 7551). Nineteen public scoping meetings
in 16 communities were held between November 18, 1992 and April
15, 1993 to solicit public input regarding the scope and content
of the PEIS (Figure 1.3).
The UMTRA Ground Water Project PEIS implementation plan summarizes
the comments received during scoping and provides DOE's response
to how the comments were addressed in the PEIS (DOE, 1994a).
A complete list of all comments received is archived in the
UMTRA Project Document Control Center.
NEPA and DOE implementing regulations also require that at
least one public hearing be for the public to comment on the
draft PEIS (10 CFR §1021.313). A notice of availability
(NOA) of the draft PEIS was published in the Federal Register
on May 17, 1995 (60 FR 26417). The NOA summarized the proposed
action, provided background information on the UMTRA Ground
Water Project, described the public comment process, and announced
the dates, times, and locations of the public hearings. Nine
public hearings were conducted in nearby site communities between
June 7 and 28, 1995 to solicit public input on the draft PEIS
(Figure 1.3).
The PEIS public affairs program provides continued opportunities
for public involvement throughout the UMTRA Ground Water Project.
This section provides an overview of the participation process
for the PEIS and the planned course of action for future public
participation in the Ground Water Project.
Figure 1.3
UMTRA Project Site And Scoping Meeting And Hearing Locations
1.6.1 Scoping process and results
DOE encouraged members of the public, tribal and state representatives,
and other agencies to participate in scoping. Notices announcing
the start of scoping were placed in the Federal Register and
advertisements were placed in local newspapers and on local
radio stations. Orientation meetings were held at some sites
to explain the scoping process to the public. Congressional
representatives and state and local agencies were contacted
during prescoping community assessments to determine the scoping
activities that would work best in individual communities. Media
briefings were held and media briefing kits were available prior
to scoping meetings to announce the opportunities for public
participation. UMTRA Project spokespersons were available before
and after scoping meetings for interviews.
Several communication methods facilitated scoping: fact sheets
were prepared and distributed that described the PEIS process,
the proposed action and alternatives, ground water contamination,
ground water remediation technologies, and site-specific conditions.
In recognition of non-English speaking community members, DOE
offered translation services upon request. At meetings held
for the Navajo Nation, a Navajo language interpreter was used
during the presentation and group discussions. A Navajo language
audio tape of the scoping materials was produced and distributed
to Navajo Nation radio stations, chapter houses, and libraries.
The scoping meetings included viewgraph presentations and small
group discussions with technical staff.
More than 500 scoping comments were received. Comments were
accepted at the scoping meetings, through the mail, and by telephone
via a toll-free number.
DOE reviewed all scoping comments. The comments generally indicated
four categories of concern: human health and the environment,
programmatic issues, ground water monitoring and site characterization,
and site-specific Surface Project comments. The PEIS Implementation
Plan (DOE, 1994a) summarizes these comments and describes how
they were to be addressed in the draft PEIS.
1.6.2 Public hearings and comment
period
A 120-day public comment period and 9 public hearings were
held after the draft PEIS was published. Information on the
availability of the draft PEIS, methods for submitting comments,
and the date, time, and place of the public hearings were announced
in the Federal Register, in local newspapers, and on radio stations.
Many of the same communication methods that were used in the
scoping meetings were used to encourage participation at the
public hearings. Both before and after media briefings, UMTRA
Project spokespersons were available for interviews and further
discussion. Fact sheets were prepared that described the PEIS
and the Ground Water Project, and translation services were
provided at hearings held at Navajo Nation and Hopi Tribe sites.
The public hearings followed an interactive format to facilitate
communications between DOE representatives and people who attended
the hearings. An independent facilitator conducted the meetings
following overview presentations by DOE UMTRA Project site managers
and Ground Water Project managers. Oral comments were recorded
on flip charts and clarified as necessary to ensure accuracy
in recording. Project personnel also responded to comments and
discussed issues raised during the meetings. More than 600 comments
were received at the public hearings, through the mail, and
by telephone via a toll-free number.
Comments received during the comment period have been evaluated
and were incorporated as applicable in this final PEIS. The
comments and response document that accompanies the PEIS identifies
all written and oral comments received, DOE's responses, and
changes made to the document, as appropriate.
1.6.3 Future public participation
activities
The final PEIS will be distributed to the public for at least
30 days before the Record of Decision is issued. The Record
of Decision will announce the DOE decision regarding how to
conduct the Ground Water Project. It also will summarize the
mitigation measures that will be taken to avoid or minimize
potential human health and environmental impacts (40 CFR §1505.2).
DOE's commitment to encouraging public participation through
public meetings with UMTRA Project representatives would continue
during site-specific ground water compliance activities at many
UMTRA Project processing sites. This would include providing
information on ground water characterization activities and
risk assessment, and seeking input regarding site-specific ground
water compliance decisions. DOE would use direct mailings and
announcements in the local media to notify the public of opportunities
to meet with DOE representatives.
Site-specific NEPA documents (for example, environmental impact
statements and environmental assessments) would be prepared
that identify the proposed ground water compliance strategy
and alternatives, analyze impacts of implementing these actions,
and specify any mitigation measures that might be necessary
to reduce adverse impacts. DOE expects that environmental assessments
will be appropriate in most cases.
If DOE determined that an environmental assessment is appropriate,
DOE would notify the host state and host tribe of the determination
to prepare an environmental assessment and would involve the
public to the extent practical during its preparation; early
public notice of the intent to prepare this document would be
provided concurrent with tribal and state notification (10 CFR
§1021.301(c); 40 CFR §1501.4(b)).
Before approving any site-specific plans, DOE would make the
plans available to the host state and tribe for review and comment,
in compliance with NEPA and DOE. Under the Secretary of Energy's
NEPA policy statement, DOE ordinarily provides enhanced opportunities
for interested persons to review and comment on environmental
assessments concurrently with tribal and state review.
In accordance with DOE policy, the UMTRA Project intends to
conduct public meetings on the site-specific plans in the affected
site communities. The DOE would solicit input from the public,
local organizations, and educational institutions on site-specific
issues that should be identified, considered, and analyzed in
the effort to meet ground water compliance