|
Programmatic Environmental Impact Statement
For The
Uranium Mill Tailings Remedial Action Ground Water Project
2.0 ALTERNATIVES
This section describes the options (alternatives) for conducting
the UMTRA Ground Water Project at the inactive UMTRA Project processing
sites and summarizes the comparison of the potential impacts of
the alternatives. These impacts are considered in detail in Section
4.0. This section also describes alternatives considered but
eliminated from further analysis, site-prioritization methodology,
risk assessment methodology, ground water characterization and
remediation methods, and waste management methods.
CEQ requires that an environmental impact statement "rigorously
explore and objectively evaluate all reasonable alternatives"
(40 CFR §1502.14(a)). Reasonable alternatives include those
that are practical or feasible from a technical and economic standpoint
using common sense, and are not simply desirable from the standpoint
of the applicant (51 FR 15618). Reasonable alternatives can be
outside the jurisdiction of the lead agency and potentially in
conflict with existing federal law. When there are many potential
alternatives, a reasonable number of examples covering the full
spectrum of alternatives must be analyzed and compared (51 FR
15618).
The simplest strategy is one in which no remediation is required.
There are two conditions where this can be used. First, if the
tailings have not contaminated the ground water, it already meets
the preexisting or background conditions; or if the contamination
is limited it may met the numerical EPA standards that are called
Maximum Concentration Limits (MCLs); i.e., the contamination is
so low that it is below the level allowed by EPA. Second, if the
concentrations of certain constituents exceed the numerical EPA
levels (the MCLs or background), there are two situations in which
the EPA has determined that cleanup is not required. (1) EPA allows
the use of Supplemental Standards. One example of Supplemental
Standards is where the ground water was of such poor quality prior
to the milling operation that removing the tailings-related contamination
from the groundwater would not raise the quality of the water
such that it would or could be used. (2) EPA allows the use of
Alternative Concentration Limits (ACLs). An ACL is a numerical
concentration for a contaminant that is higher than the Maximum
Concentration Limit in the EPA standards or background, but for
which is can be shown that human health and the environment would
not be adversely affected in a particular situation. If ACLs are
used, the Department must demonstrate that the higher levels of
contamination do not pose an excessive health risk.
At the next level is Natural Flushing. Once the surface tailings
and other contaminated materials are contained in disposal cells,
contamination of the groundwater should greatly diminish. At some
of the sites, the natural processes of nature will attenuate the
contamination over time. If these natural process can reduce the
contamination to an acceptable numerical levels such as MCLs background
or ACLs within 100 years, the use of natural flushing is permitted
by the EPA standards. Under this strategy the Department must
demonstrate through analysis that the constituents will be reduced
by natural flushing within 100 years or less. If approved, monitoring
will continue and if the natural flushing does not work as predicted,
DOE would then have to propose and implement a more active strategy.
One element of implementing natural flushing that is permitted
by the EPA standards is the use of institutional controls. Institutional
controls protect public health by alternative means; for example,
government ownership of the contaminated area or State/local restriction
on the use of contaminated ground water.
Table 1. Ground water compliance strategies that apply under
each alternative
Alternative
|
Strategy
|
Proposed action
|
No actiona
|
Active
remediation to background
levels
|
Passive
remediation
|
| Active ground water remediation methods |
X |
|
Xb |
|
| Natural flushingc |
X |
|
|
X |
No ground water remediation
- Sites that qualify for supplemental standardsd
or alternate concentration limits.e
- Sites that meet maximum concentration limits or
background levels (no impacts).
|
X
X |
|
|
X
X |
aThe analysis of the no action alternative is required
by the CEQ and DOE.
bActive remediation methods would not be used at
sites where contamination does not exceed background and likely
would not be used at sites that qualify for supplemental standards
based on the existence of limited use ground water.
cNatural flushing means allowing the natural ground
water movement and geochemical processes to decrease contaminant
concentrations.
dSupplemental standards applicable for certain site
conditions, as identified in the EPA standards, that are protective
of human health and the environment, and may be applied in lieu
of prescriptive levels.
eConcentrations of contaminants that may exceed the
maximum concentration limits; or, limits for those constituents
without maximum concentration limits. If DOE demonstrates, and
NRC concurs, that human health and the environment would not
be adversely affected, DOE may meet an alternate concentration
limit.
f"No remediation" at sites that do not
exceed maximum concentration limits or background levels is
not the same as "no action" because these sites would
require activities such as site characterization to show that
no remediation is warranted.
Finally, the most complex strategy is Active Remediation. If
there is excessive contamination and if natural processes will
not attenuate it quickly, active control or removal of the contamination
is necessary. The classic approach is to pump the contaminated
water and treat it to remove the contamination, but other, newer,
more effective technologies may also be possible.
The process of selecting a site-specific strategy includes several
steps that are not explicitly required by the current regulations,
but will help in selecting the best strategy. One of these is
to prepare a Baseline Risk Assessment (BLRA). The BLRA is prepared
after initial characterization of a site. It provides a detailed
analysis of human and environmental exposures to all of the known
contaminants of concern. Risks can then be evaluated to determine
the appropriate strategy. Another is the Site Observational Work
Plan (SOWP). The SOWP addresses the ground water conditions at
a site and documents how DOE will demonstrate compliance with
the standards. It includes the various techniques that will be
used to further characterize a site and is the basis for making
the final recommendation to the regulator. Numerous alternatives
were evaluated during the planning stages of the PEIS. Five alternatives,
including the proposed action, were included in the published
Notice of Intent to prepare the PEIS (57 FR 54374). These alternatives
represented a preliminary list; public comment on these and other
alternatives was part of prescoping and scoping meetings (DOE,
1994a). As a result of the scoping process and other planning
activities, four alternatives, including the proposed action,
were selected for analysis in this PEIS. The four alternatives
are as follows:
- Proposed action-DOE would use a consistent, risk-based decision
process to comply with the EPA standards at the processing sites.
The DOE would use active, passive, and/or no remediation ground
water compliance strategies to meet the EPA ground water standards
at the UMTRA Project sites. The site-specific ground water compliance
strategies would be based on site conditions, potential risks,
and input from the affected tribes, states, and public.
- No action-DOE would not conduct the UMTRA Ground Water Project.
Contaminated ground water would remain as is, and no further
action would be made to protect human health and the environment.
- Active remediation to background levels-DOE would use a combination
of active remediation strategies at most sites to clean up ground
water quality to as close to background levels as possible and
meet the EPA ground water standards.
- Passive remediation-DOE would use natural flushing or no other
remediation strategies, including application of alternate concentration
limits and supplemental standards, to meet the EPA ground water
standards.
These four alternatives are discussed in detail in Sections
2.1 through 2.4. The EPA ground water standards
are described in Section 1.4.1.
The potential programmatic impacts of implementing the proposed
action and alternatives are provided in Section
4.0.
This PEIS differs substantially from a site-specific environmental
impact statement because multiple ground water compliance strategies,
each with its own set of potential impacts, could be used to implement
all the alternatives except the no action alternative. In a traditional
environmental impact statement, the identification of alternatives
leads directly to an impacts analysis. On the other hand, an impacts
analysis for implementing alternatives in this PEIS involves an
intermediate step of evaluating a ground water compliance strategy
or strategies, the use of which would result in site-specific
impacts. This PEIS impacts analysis assesses the potential impacts
of the various ground water compliance strategies, then relates
them to the alternatives to compare impacts.
2.1 PROPOSED ACTION (Preferred Alternative)
The proposed action, which is DOE's preferred alternative,
would select a ground water compliance strategy tailored for
each site to achieve conditions that are protective of human
health and the environment. The proposed action would consider
the full range of ground water compliance decisions in a step-by-step
approach, beginning with consideration of the "no remediation"
strategy and proceeding, if necessary, to the passive strategy,
such as natural flushing with compliance monitoring and institutional
controls, and to a more complex, active ground water cleanup
methods, such as pump and treat or other engineered approaches
to cleaning up contaminated ground water. For example, under
the proposed action, if a site risk assessment and site observational
work plan indicate that the strategy of "no remediation"
would be in compliance with the EPA standards and be protective
of human health and the environment, a more complex strategy
involving active cleanup methods would not be necessary.
The proposed action is intended to establish a consistent risk-based
framework for implementing the UMTRA Ground Water Project and
determining appropriate ground water compliance strategies at
the UMTRA Project former processing sites. The determination
of site-specific ground water compliance strategies would take
into account site-specific ground water conditions; human and
environmental risks; participation of the Tribes, States, and
local communities; and cost. This approach is sufficiently flexible
to allow for interim actions, such as an alternate water supply
systems, should these activities be necessary in order to reduce
risk and/or support institutional controls. The proposed action
would also allow the consideration of new ground water cleanup
methods that become available.
The proposed action uses a logic framework to identify the
appropriate ground water compliance strategy or strategies for
a site (Figure 2.1). Each step in the
decision process considers meeting the EPA standards and the
protection of public health and the environment in determining
the appropriate strategy to meet ground water protection standards.
The first step in the decision process would be to determine
if the uranium processing activities at a specific site have
resulted in ground water contamination exceeding background
levels or maximum concentration limits (Figure
2.1). If ground water contamination has not exceeded these
standards and is not expected to, remediation would not be required.
Figure 2.1
Proposed Action
If ground water has been contaminated by uranium processing
activities and the contamination exceeds background levels or
maximum concentration limits, the next step would be to determine
if compliance with the EPA ground water standards could be achieved
by applying supplemental standards based on the existence of
limited use ground water. (Refer to Section
1.4.1 for a discussion of supplemental standards.) If limited
use ground water were shown to exist and if supplemental standards
were protective of human health and the environment, no site-specific
remediation would be required. If supplemental standards based
on limited use were not protective, the next step would be to
determine whether alternate concentration limits would apply.
(Refer to Section 1.4.1 for
a discussion of alternate concentration limits.) If alternate
concentration limits were protective of human health and the
environment, alternate concentration limits would be applied.
If not, it would be necessary to determine whether the contaminated
ground water plume would qualify for supplemental standards
based on the criterion that remediation would cause more environmental
harm than benefit. At some sites where supplemental standards
or alternate concentration limits may be applied, ground water
monitoring and institutional controls may be required to ensure
that the application of alternate concentration limits or supplemental
standards would continue to be protective of human health and
the environment. In addition, when limited use ground water
applies, supplemental standards "shall ensure that current
and reasonably projected uses of the affected ground water are
preserved" (60 FR 2854). The use of supplemental standards
would be determined on a site-by-site basis and the DOE would
abide by the EPA ground water standards when proposing the use
of supplemental standards. All proposed supplemental standards
would require U.S. Nuclear Regulatory Commission concurrence.
If supplemental standards would not be protective, the next
step would be to determine whether natural flushing would bring
the contaminated ground water into compliance (i.e., within
maximum concentration limits, background levels, or alternate
concentration limits) within 100 years. Natural flushing is
a ground water remediation strategy by which natural ground
water processes result in compliance with the EPA ground water
standards. (Refer to Section 1.4.1
for a discussion of EPA standards related to natural flushing.)
Natural flushing could be used if it were determined that institutional
controls could be implemented, maintained, and enforced during
the natural flushing period; that this strategy was protective
of human health and the environment; and that all other conditions,
as described in Section 1.4.1,
are met.
If natural flushing would not be protective, it would be necessary
to determine whether natural flushing combined with active remediation
methods would meet the EPA ground water standards and would
be protective of human health and the environment. If so, this
two-part strategy would be implemented. When combined with natural
flushing, active remediation methods could be used for a short
time to remove the most contaminated ground water that may occur
in a restricted area; then natural flushing would be applied.
Another option would be to use low-operation and low-maintenance
active methods, such as gradient manipulation or geochemical
barriers, in conjunction with natural flushing.
Site characterization data may show that natural flushing combined
with active remediation would not result in ground water quality
that is protective of human health and the environment. That
being the case, the next step in the framework would be to determine
if active ground water remediation techniques would meet the
EPA ground water standards and if so, to implement these techniques.
Several methods of active ground water remediation could be
used, including gradient manipulation, ground water extraction,
and in situ ground water treatment. The active remediation methods
could be used individually or in combination with other cleanup
methods. Section 2.8 provides details on
active ground water remediation methods. If active remediation
resulted in compliance with the EPA standards, remedial action
would be complete. If these methods did not result in compliance,
supplemental standards based on technical impracticability of
remediation would be applied, along with institutional controls
where necessary.
The proposed action is sufficiently flexible to allow for alternate
water systems or interim actions should these activities be
necessary in order to reduce risk and/or support an institutional
control.
2.2 NO ACTION
The regulations for preparing an environmental impact statement
require that the no action alternative be assessed (40 CFR §1502.14(d)),
even if the agency is under a legislative mandate to act (51
FR 15618). The analysis of the no action alternative "provides
a benchmark, enabling decision makers to compare the magnitude
of environmental effects of the action alternatives" (51
FR 15618).
Under the no further action alternative, no further activities
would be conducted to comply with the EPA ground water standards
at the inactive UMTRA Project processing sites. The UMTRA Surface
Project would be completed but the Ground Water Project would
be terminated and the contaminated ground water would be left
as it is. DOE would not collect ground water data to continue
characterization of ground water, no monitoring of contaminated
ground water would take place, and no institutional controls
would be used.
The no action alternative would comply with the EPA ground
water standards only at the site where there is no ground water
contamination (the Lowman, Idaho, site).
2.3 ACTIVE REMEDIATION TO BACKGROUND LEVELS
Under this alternative, the DOE would attempt to clean up ground
water to background levels at the UMTRA Project processing sites,
using active ground water remediation methods. This attempt
would be limited by the technology available. Therefore, it
may not be possible to restore some contaminated ground water
to background levels. In these cases, the DOE would attempt
to reduce contamination to levels as closely as possible to
background levels. The rationale behind this alternative is
that ground water at most of the uranium processing sites was
of better quality before the processing activities occurred
and that the ground water should be restored to its preprocessing
quality. At most UMTRA Project processing sites, implementation
of this alternative would require the use of active ground water
remediation methods such as gradient manipulation, ground water
extraction and treatment, or in situ ground water treatment
(active ground water remediation methods are summarized in Section
2.8). Active remediation methods would be used at the UMTRA
Project processing sites regardless of the health and environmental
effects and regardless of cost and time. Because active remediation
methods would be required at most UMTRA Project processing sites,
this alternative would likely reduce the potential risks associated
with the ground water contamination and would be protective
of human health and the environment.
If this alternative were implemented, DOE would meet the EPA
ground water standards at the UMTRA Project sites. Active ground
water remediation methods would not be used at sites where the
ground water quality beneath the site is currently at background
levels and likely would not be used at sites that qualify for
supplemental standards based on the existence of limited use
ground water.
Under the active remediation to background levels alternative,
alternate water systems or interim actions could be used should
they be necessary to reduce risk and/or to support an institutional
control.
2.4 PASSIVE REMEDIATION
The implementation of this alternative would result in the
use of only passive remediation strategies to meet the EPA ground
water standards. The passive remediation strategies are 1) performing
no remediation at sites that meet supplemental standards or
alternate concentration limits, or are at background levels
or below maximum concentration limits; and 2) relying on natural
flushing. This alternative uses site characterization and risk
assessments to determine the most appropriate passive remediation
strategy for each site. However, risk assessment and other data
may indicate that passive remediation strategies alone would
not be protective of human health and the environment at all
processing sites.
This alternative is distinct from the no action alternative
because, as indicated in Section 2.2, under
the no action alternative, activities would not be conducted
to restore contaminated ground water at the UMTRA Project sites.
In addition, the Ground Water Project would be terminated and
the contaminated ground water would be left as is. Under the
passive remediation alternative, site characterization would
take place before the determination of the appropriate ground
water compliance strategy. Ground water monitoring would take
place where needed. In addition, institutional controls would
be used, if necessary to protect human health and the environment.
In general, if this alternative were implemented, DOE would
follow the same initial steps as for the proposed action (Figure
2.1). However, the final step for this alternative would
be to determine whether natural flushing would result in meeting
background levels, maximum concentration limits, or alternate
concentration limits. Institutional controls and monitoring
generally would be required to restrict access to contaminated
ground water (refer to Section 1.4.1
for a discussion of natural flushing and institutional controls).
For sites where natural flushing would reduce the concentrations
of contaminants to below the standards in less than 100 years
and be protective of human health and the environment, the EPA
ground water standards would be met.
Under the passive remediation alternative, active remediation
would not be conducted at a site, even if compliance with the
EPA ground water standards would not be met. At sites that would
not meet standards within 100 years, institutional controls
and monitoring would be required for more than 100 years. This
would result in noncompliance with the EPA ground water standards
and may not protect human health and the environment. The passive
remediation alternative may not be protective of beneficial
uses of the ground water, such as irrigation or livestock watering.
Under the passive remediation alternative, alternate water
systems or interim actions could be used should they be necessary
to reduce risk and/or to support an institutional control.
2.5 COMPARISON OF ALTERNATIVES
In accordance with CEQ regulations (40 CFR §1502.14),
this document compares the four alternatives and summarizes
their potential impacts. The comparison of alternatives below
summarizes the detailed comparison found in Section
4.4.
The qualitative analysis of potential impacts of the ground
water compliance strategies (Section
4.2) and of the no action alternative (Section
4.3) were used to compare the potential impacts of the alternatives
(Section 4.4). The assumptions
used to compare the alternatives also appear in Section
4.4.
The potential impacts of the alternatives can be divided into
short-term and long-term impacts. Short-term impacts are associated
with site characterization and the construction of ground water
facilities. Long-term impacts are those that could occur if
the ground water remediation was not remediated or if ground
water remediation took many years.
Short-term potential impacts
The proposed action and the active remediation to background
alternative would require site characterization, monitoring,
and construction of remediation facilities. The passive remediation
alternative would require site characterization and monitoring.
Potential impacts to air quality, noise levels, visual resources,
transportation systems, utilities, and energy supplies would
occur principally during site characterization and during the
construction of ground water remediation facilities for the
proposed and the active remediation to background levels alternatives.
As indicated in Section 4.4, the
alternatives would have little or no impact on these resources
due to the short duration and small scale of the ground disturbance
activities. Site characterization, construction, and monitoring
activities have the potential to disturb sensitive habitats,
species, cultural resources, and land use. However, these impacts
potentially can be avoided by conducting site characterization
and remediation activities in areas away from these resources.
In addition, if impacts to these resources occurred, their effects
could be mitigated. Therefore, the potential for site characterization
and construction activities to adversely affect these resources
would be considered relatively minor. Impacts to land use could
also occur.
Long-term potential impacts
Based on the analysis in Section
4.0, long-term adverse impacts could arise under the following
circumstances:
- If the contaminated ground water did not meet EPA standards
and was not controlled. This would occur under the no action
alternative.
- If the ground water compliance strategy were not protective
of human health and the environment. This could occur under
the passive remediation alternative.
- If institutional controls were in place for many years.
This could occur under all the alternatives except the no
action alternative.
Implementing the no action alternative would not comply with
the EPA standards at all UMTRA Project processing sites. As
a result, significant long-term adverse impacts to human health
and the environment could occur under the no action alternative.
For example, the public could be exposed to site-related hazardous
contaminants by drinking contaminated ground water or surface
expression of ground water, ingesting contaminated livestock
and/or plants, or ingesting contaminated fish and/or wildlife.
Adverse impacts to wildlife could occur if the contaminants
entered the food chain and/or affected sensitive resources such
as wetlands or threatened and endangered species.
Potentially adverse impacts would be less likely under the
proposed action or the active remediation to background alternative
because all UMTRA Project sites would comply with the EPA standards.
In addition, surface and ground water monitoring would take
place before and during implementation of the proposed action
and the active remediation to background alternative to ensure
that protective measures could be maintained or implemented,
if necessary.
Implementation of the passive remediation alternative also
could result in the exposure of humans and the environment to
site-related hazardous contaminants. The potential occurrence
of such impacts is less than from the no action alternative,
but such impacts could occur at sites where hydrogeological
data and risk assessments have demonstrated that the use of
passive ground water remediation strategies would not be protective
of human health and the environment. For example, this could
occur at sites where institutional controls are not viable or
would not effectively restrict access to contaminated ground
water or at sites where the potential ecological risk from contaminated
surface expression of ground water (now or in the future) cannot
be avoided or prevented with passive remediation strategies.
These potential long-term impacts would have a low probability
of occurring under the proposed action or the active remediation
to background alternatives.
Institutional controls can be used in conjunction with natural
flushing for up to 100 years. These controls may need to be
used even longer with the passive remediation alternative because
contaminant plumes may still exist after 100 years of natural
flushing. The use of institutional controls could result in
long-term land use and socioeconomic impacts, as discussed in
Sections 4.4.6 and 4.4.11.
The passive remediation alternative could have the greatest
impact in this area, followed by the proposed action, then the
active remediation to background alternative.
In summary, the proposed action and the active remediation
to background alternatives are most effective at protecting
human health and the environment because under these alternatives
all of the UMTRA Project sites would comply with the EPA standards.
Implementing the proposed action would potentially result in
fewer impacts than implementing the active remediation alternative.
The proposed action would potentially be more cost-effective
because it would use passive remediation strategies such as
natural flushing or no remediation at sites where these strategies
are shown to be protective of human health and the environment
and meet the EPA standards. The active remediation alternative
would be the most costly because of its widespread use of active
ground water compliance methods. Under this alternative, active
methods would be used at sites where active remediation is justified
under the proposed action based on site-specific risk assessments.
In addition, active remediation would also be used at many sites
where no additional risk reduction would occur as a result of
active remediation.
2.6 ALTERNATIVES ELIMINATED FROM ANALYSIS
CEQ regulations require that an environmental impact statement
1) evaluate all reasonable alternatives, 2) briefly discuss
those alternatives eliminated from detailed impact analysis
in the environmental impact analysis, and 3) provide the reasons
for their elimination (40 CFR §1502.14(a)).
Reasonableness is defined as practical or feasible from a common
sense, technical, and economic standpoint (51 FR 15618). Four
alternatives were considered early in the PEIS planning stages
but were eliminated from further evaluation. A fifth alternative,
use of tribal and state standards, was considered as a result
of comments received on the draft PEIS, but was eliminated from
further consideration. All these alternatives and the reasons
for their elimination are provided in the following subsections.
2.6.1 Delay the UMTRA Ground Water
Project
Delaying the Ground Water Project until the Surface Project
is completed was not considered a viable alternative because
surface remediation is complete at 18 sites and resources have
become available to address ground water compliance. To further
delay ground water remediation at some of the processing sites
may not be protective of human health and the environment.
2.6.2 Use existing data to make Ground
Water Project decisions
Under this alternative, no new site characterization or risk
assessment data would have been collected at any of the sites.
The UMTRA Ground Water Project would have proceeded using only
existing data. Existing site characterization data include geologic,
hydrogeologic, geochemical, geotechnical, and radiological conditions
at the processing sites. These data were collected for the purposes
of designing and implementing surface remediation. This information
may not have fully characterized ground water conditions, leading
to the possibility of making incorrect decisions regarding site-specific
ground water compliance; therefore, this alternative was not
considered further.
2.6.3 Provide clean water at the point
of use
This alternative would have required the DOE to provide an
alternate water source at the point of any use in situations
where ground water used by humans has become or soon would become
contaminated. Clean water sources could have been bottled water,
connection to a municipal water supply, or new wells tapping
uncontaminated ground water resources. Under this alternative,
the DOE would not have complied with EPA standards.
This alternative was considered because it meets the immediate
purpose and need of protecting human health and agricultural
applications. It was eliminated from detailed study for the
following reasons:
- A basic assumption in regard to this alternative is that
the DOE would provide an alternate water source at the point
of human use (e.g., domestic water sources, livestock watering,
and/or crop irrigation) but would do nothing to protect the
biological communities from the contaminated ground water.
Therefore, use of this alternative would not be protective
of the environment since contaminated ground water could discharge
into rivers, streams, wetlands, and other biological systems.
Furthermore, these biological systems would not be monitored
so the degree of contamination, if any, would not be known.
This raises the possibility of contaminants entering the biological
foodchain which could include humans.
- The use of this alternative would require ground water monitoring
to determine the location of the plume over time and changes
in the level of contamination to determine if the plume is
nearing points of use not previously protected. In some cases,
this monitoring would be needed for a very long period of
time because plumes at some of the UMTRA Project sites move
slowly.
- This alternative would not meet the EPA standards at all
sites. In one sense, this alternative would have to continue
until the threat to human health no longer exists. The EPA
standards stipulate that ground water contaminants must meet
the standards within 100 years. Under this alternative, meeting
the standards within 100 years may not occur at all sites.
- Treatment at the point of use is not excluded from the alternatives
analyzed in the PEIS (except no action). If the drinking water
(or other beneficial uses) is threatened at a given site during
the Ground Water Project, DOE may provide an alternate source.
- Treatment at the point of use that includes institutional
controls is the same as the passive remediation alternative.
Sites that require institutional controls for the passive
remediation alternative also would require institutional controls
under the treatment at the point of use alternative, so as
to reduce the likelihood of using contaminated ground water.
2.6.4 Achieve ground water compliance
without a programmatic approach
This alternative would have required the UMTRA Ground Water
Project to proceed without a programmatic approach. This would
have meant that ground water compliance would have been treated
as discrete tasks for each site. Compliance with EPA's ground
water standards would have been met at all processing sites.
All NEPA and technical documents would have been produced independently
of one another. Scheduling of site activities would have been
based on preliminary risk prioritization data.
This alternative was eliminated from further analysis because
it would have had many variables and the determination of potential
environmental impacts would not be meaningful. In addition,
it is not consistent with CEQ regulations, which consider related
activities a single course of action (for example, the UMTRA
Ground Water Project) that must be evaluated in a single impact
statement (40 CFR §1502.4(a)).
2.6.5 Use tribal and state standards
Even though the UMTRCA requires DOE to meet the EPA standards,
this alternative would require the UMTRA Project to use tribal
and state standards, where they exist, rather than EPA standards.
Because the UMTRA Project sites are in 10 different states and
on or near lands of four different tribes, the UMTRA Project
could be subject to 14 different sets of standards administered
by 14 different agencies. This approach would be unacceptable
because:
- The standards for specific constituents likely vary from
agency to agency, which could lead to unequal treatment of
the sites.
- Some agencies may have standards for specific constituents
while others may not have a standard for that specific constituent.
This could also lead to unequal treatment of the sites.
- Jurisdictional problems would likely arise under this alternative.
For example, an UMTRA site may be on land under the jurisdiction
of one agency, but a contaminated ground water plume may cross
the border into the jurisdiction of another agency.
- This alternative would likely increase remedial action costs
due to the DOE's having to address so many sets of standards.
- Preparing site-specific ground water compliance documents
and implementing the site-specific ground water compliance
strategies would be difficult, given the large number of varying
standards that would have to be addressed.
2.7 SITE PRIORITIZATION AND RISK ASSESSMENT
2.7.1 Site prioritization
Site prioritization ensures that appropriate, relevant, and
objective considerations are given to each site during planning
stages. The cumulative scores of each site are ranked to determine
which sites have the greatest urgency for early actions.
The prioritization system developed for the UMTRA Ground Water
Project is based on the UMTRA modified Environmental Restoration
Priority System which used multiattribute utility analysis to
prioritize sites. This system is described in detail elsewhere
(DOE, 1991a) and is summarized here.
This prioritization approach was shared in draft with all the
affected tribes and states. Comments were rigorously encouraged.
The DOE conducted meetings on the application of this prioritization
methodology with three states and two tribes.
The six criteria below were used to prioritize the sites; for
each UMTRA site, each criteria was scored from 1 to 7. A score
of 1 indicates conditions defined by the factor are acceptable,
while a score of 7 indicates highly unfavorable conditions.
Population health risk
This criterion is based on annual health risks to potentially
affected populations (i.e., populations consuming ground water
directly or indirectly). It can be extrapolated from individual
risks calculated in ground water risk assessments, or can be
determined by using EPA Hazard Ranking Scores for the ground
water exposure pathway.
On the population health risk scale, a score of 7 is equivalent
to the occurrence or likely occurrence of 10 adverse health
effects per year. The scale decreases logarithmically to 1,
which signifies an annual population risk of 1 in 10,000,000.
Individual health risk
This criterion is based on increased individual risks over
a lifetime from direct or indirect consumption of ground water.
These values are calculated from worst-case, point-of-exposure
wells. If the water quality in the area is unsuitable for drinking,
another pathway (such as crop irrigation or livestock watering)
may be calculated.
These risks are based on the EPA's Risk Assessment Guidance
for Superfund documents and produce results in the form of a
hazard index and carcinogenic risk. These scores are converted
to a logarithmic scale of 1 to 7, where 1 signifies an individual
lifetime risk of 1 in 10,000,000, and 7 signifies a risk of
1 in 10.
Timing
Timing is an important factor in prioritizing ground water
restoration sites because it quantitatively incorporates the
current or anticipated use of ground water. Sites where affected
ground water is in use should have higher priority than sites
where alternate water supplies are abundant, accessible, and
inexpensive. This criterion makes the risk estimates more meaningful
since it ties them to actual site factors (such as probability
of ground water use).
Additionally, hydrologic factors such as aquifer flushing time,
contaminant migration rate, or increased plume spread can be
incorporated into the timing criterion.
Environmental risk
The baseline environmental risk scores are determined from
the product of two factors:
- The sensitivity of the environmental resource at risk.
- The magnitude of the threat associated with the contaminated
ground water.
The definition for sensitivity of resources was adapted from
the EPA's Final Hazard Ranking System (40 CFR Part 300) and
includes scenic or wild rivers, unique riparian habitats, wetlands,
threatened or endangered species, spawning areas, or any critical
habitat. The threat to these resources is based on largely qualitative
criteria (including criteria for exceedance of ambient water
quality and observed contaminant uptake or toxicity in biota)
and threats to the population abundance.
Socioeconomic impact
Socioeconomic impact scores are derived from three components:
- Public concern.
- Cultural/traditional impacts.
- Community losses/opportunity costs.
The first factor scores public and political interest. This
is significant on the UMTRA Project because many stakeholders
are very concerned about ground water restoration.
The second factor, cultural impacts, is significant primarily
to tribal sites. It recognizes the spiritual values the Hopis
and Navajos associate with their ground water.
The last factor is used to score economic impacts to a community
that loses the use of an affected aquifer. This factor relates
to the size of the contaminant plume as well as the demand for
its use.
Regulatory noncompliance
The primary criterion in this factor was compliance with applicable
ground water standards, including tribal or state laws addressing
ground water.
After each factor was scored, the scores were weighted as follows:
20 percent for population risk; 30 percent for individual risk;
10 percent for timing factors; 15 percent for environmental
impacts; 15 percent for socioeconomic considerations; and 10
percent for regulatory noncompliance.
Sites were assigned to one of five groups based on this prioritization,
allowing for flexibility in planning compliance activities.
Category I sites with the highest priority are New Rifle, Old
Rifle, and Gunnison, Colorado; Tuba City, Arizona; and Riverton,
Wyoming. The Gunnison Category 1 classification does not take
into account the implementation of the alternate water supply.
Category II sites with the next highest priority are Monument
Valley, Arizona; Lakeview, Oregon; Shiprock, New Mexico; and
Durango, Colorado. Category III sites are Naturita, Slick Rock,
and Grand Junction, Colorado; and Green River and Salt Lake
City, Utah. Category IV sites are Bowman and Belfield, North
Dakota; Canonsburg, Pennsylvania; Falls City, Texas; and Maybell,
Colorado. Category V sites are Ambrosia Lake, New Mexico; Mexican
Hat, Utah; Lowman, Idaho; and Spook, Wyoming. The UMTRA Ground
Water Project site prioritization system took into account the
likelihood that exact scores, and therefore priority, may change
as additional data are gathered.
The site prioritization groups would be considered when site-specific
decisions are being made. Ground water remediation at the sites
would be further prioritized based on additional health or environmental
risk information. The following factors would be taken into
account when determining the risk at a site:
- Is the contaminated ground water likely to be used soon?
- How much contamination is present?
- How toxic is the contaminated ground water?
- Can access to the ground water be controlled?
Prioritization is one element of the Ground Water Project.
It would be applied objectively to the maximum extent possible.
2.7.2 Site-specific risk assessments
The purpose of the UMTRA Ground Water Project baseline risk
assessments is to determine whether there is current use of
the contaminated ground water and whether ground water contamination
at the former processing sites has the potential to adversely
affect public health or the environment. The results of the
site-specific baseline risk assessments are or would be used
to:
- Evaluate potential current and future public health and
ecological risks at the sites.
- Determine the need for an alternate water supply, based
on the potential for adverse human health effects.
- Identify additional data, if any, needed to characterize
risks at UMTRA sites.
- Determine current and potential future land uses at and
near the sites.
- Inform the public of current and/or future potential public
health and ecological risks.
- Help determine site-specific ground water compliance strategies.
- Determine whether access to ground water should be restricted
through the use of institutional controls.
As indicated in Section 2.1 and as shown
in Figure 2.1, the proposed action
is a health and environmental risk-based approach for implementing
the Ground Water Project. The risk assessments and the ground
water characterization data would be used to help determine
the appropriate ground water compliance strategies that would
be implemented at each UMTRA Project site.
The baseline risk assessments have been or will be made available
to the public and libraries near the sites. If the risk assessment
identified a significant health risk associated with short-term
use of ground water near the sites, mechanisms for restricting
access to the ground water would be discussed.
Because the baseline risk assessments are being conducted in
the early stages of the Ground Water Project, they may be prepared
before comprehensive characterization of the contaminant plume
is complete at some sites. The baseline risk assessments identify
data gaps and recommend additional data collection efforts.
After site characterization is completed, risk assessments may
be updated, if necessary.
Risk assessments would be used in deciding how to meet the
UMTRA ground water protection standards. In developing site-specific
ground water compliance strategies under the proposed action,
the baseline risk assessments would be used to determine if
a given strategy would be protective of human health and the
environment. As indicated on Figure 2.1,
protection of human health and the environment is considered
in the application of all ground water compliance strategies.
For example, if supplemental standards based on limited use
ground water were considered for a site, the risk assessment
would analyze any potential health effects of consuming contaminated
ground water, and consider potential adverse effects on other
beneficial uses (e.g., agricultural or industrial). The assessment
also would address the potential impacts of contaminated ground
water on area plant and animal communities. If supplemental
standards based on limited use are determined to be protective
of human health and the environment and all other requirements
can be met, this strategy may be proposed for a site.
Risk assessments also could be used on the Ground Water Project
to assess the risks of natural flushing. As indicated in Section
1.4.1, the use of natural flushing is permitted if it would
result in meeting background levels, maximum concentration limits,
or alternate concentration limits within 100 years; if institutional
controls would protect public health and the environment from
the contaminated ground water; and if ground water is not currently
or projected to become a source of public drinking water. The
risk assessment would be an important tool in determining the
protectiveness of proposed alternate concentration limits; determining
if the public would be protected from exposure to contaminated
ground water; determining the potential for contaminated ground
water to adversely affect biological resources; and determining
if the contaminated ground water could be used as drinking water
or for other beneficial uses.
Appendix B describes the human health and ecological risk assessment
methodologies used on the UMTRA Ground Water Project.
2.8 GROUND WATER CHARACTERIZATION AND REMEDIATION
METHODS
The nature and extent of ground water contamination must be
evaluated before a ground water compliance strategy can be determined.
The former processing sites must be characterized to the extent
necessary to 1) define the physical, chemical, and biological
conditions at the sites; 2) identify the sources and extent
of contamination related to processing activities; and 3) obtain
additional data that will be used with historical data in evaluating
potential impacts to human health and the environment. A ground
water compliance strategy for a particular site would be selected
only after adequate hydrogeological and geochemical characterization
is completed. Hydrogeological and geochemical characterization
activities would reduce uncertainties to the extent practical,
to ensure the compliance strategy selected would be protective
of human health and the environment.
At UMTRA Project sites, inorganic contaminants are the principal
constituents that have been found in underlying aquifers. Hazardous
constituents that have exceeded maximum concentration limits
in ground water at UMTRA Project sites include arsenic, cadmium,
chromium, lead, molybdenum, nitrate, selenium, radium-226 and
-228, net gross alpha, and uranium. Additional metals that do
not have maximum concentration limits have exceeded background
concentrations at some sites. This section summarizes ground
water characterization requirements and processes. These characterization
methods may be implemented for all alternatives except the no
action alternative. More detailed descriptions of ground water
characterization methods are presented in Appendix C.
2.8.1 Site hydrogeologic and geochemical
characterization
Ground water characterization
Under the proposed action, ground water characterization for
the UMTRA Ground Water Project would be consistent with the
requirements of Subpart B and Subpart C of the EPA ground water
protection standards. In support of the proposed action, three
programmatic documents would provide guidance for ground water
characterization and compliance and ensure project continuity
and consistency: the Technical Approach to Groundwater Restoration
(DOE, 1993a), the Guidance Document for Preparing Water Sampling
and Analysis Plans for UMTRA Sites (DOE, 1993b), and the
UMTRA Project Technical Assistance Contractor Quality Assurance
Implementation Plan for Surface and Ground Water (DOE, 1994b).
These documents would also provide guidance for the Ground Water
Project if either the active remediation to background or passive
remediation alternative became the proposed action. If the no
action alternative became the proposed action, these documents
would not be used because future work on the Ground Water Project
would cease.
The Technical Approach to Ground Water Restoration provides
technical guidance for implementing the Ground Water Project.
This document addresses the regulatory basis and requirements
for ground water compliance, ground water characterization and
remediation methodologies, and the requirements for meeting
NRC concurrence.
The Guidance Document for Preparing Water Sampling and Analysis
Plans for UMTRA Sites provides a consistent technical approach
for water sampling and monitoring activities to be performed
under site-specific water sampling and analysis plans. The plans
would identify and justify specific sampling locations, ground
water constituents for analysis, detection limits, and sampling
frequency for the ground water and surface water sampling locations.
The Quality Assurance Implementation Plan describes
the policy, organization, functional activities, and quality
assurance and quality control protocols for environmental characterization.
It provides specifications for collecting and analyzing environmental
samples and assessing data. It also addresses quality issues
associated with data and samples related to geology, hydrology,
chemistry, biology, and engineering.
Assuming that one of the PEIS alternatives other than the no
action alternative is implemented, the technical guidance in
these three programmatic documents would be used to prepare
site observational work plans. The site observational work plan
would present the initial evaluation of existing information
related to each site, a conceptual site model of the hydrogeological
and geochemical processes, and additional data needed to adequately
characterize the ground water conditions. Further data collection
would be of sufficient quality and quantity to support future
project planning and the necessary activities associated with
the ground water compliance strategy selection and implementation.
The impacts of the proposed ground water compliance strategy
would be assessed in site-specific environmental documents.
Baseline risk assessments have been prepared for most sites.
When relevant and applicable, these assessments would be modified
and updated as additional monitoring and site characterization
data are obtained. Site-specific remedial action plans would
be prepared for sites where an active ground water remediation
strategy would be most appropriate, or the Surface Project remedial
action plan would be modified.
The observational method would be used during the planning
for and collection of site characterization data. The observational
method is an approach that would establish a ground water characterization
plan and remedial action based on most probable site conditions;
identify reasonable variations from those conditions; identify
parameters for detecting variations from the most probable conditions
during characterization and compliance; and provide plans for
addressing potential variations (Peck, 1969). The observational
method would be an effective and economical means to manage
uncertainties associated with remediating ground water resources.
Examples of currently available data for the UMTRA Project
sites include information on hydrogeologic properties, background
ground water quality, contaminant sources, hazardous constituents
in ground water, and ground water use, value, and alternative
supplies. The extent of ground water characterization during
the Surface Project depended on the preferred disposal alternative.
Processing sites with disposal cells within their boundaries
were characterized in greater detail to justify their selection,
provide data for disposal cell design, define the extent of
surface contamination, and generate a defensible ground water
protection strategy for surface remediation that was protective
of human health and the environment. The processing sites where
surface remediation activities were completed or were in progress
before the EPA ground water regulations were issued generally
were characterized to a lesser extent.
For processing sites where contaminated materials were or will
be removed off the site, characterization efforts consist of
defining tailings-related ground water contamination and determining
if conditions at the processing site would adversely affect
human health and the environment.
Site-specific ground water characterization would require short-term
activities on or near the site. To carry out characterization
activities, a crew of 10 or fewer people would be on the site
temporarily to conduct activities such as drilling monitor wells,
constructing access roads, and excavating test pits. Support
vehicles and heavy equipment (for example, drilling rigs) may
use roads around the site for brief periods. Certain ground
water characterization activities would require electrical power.
For example, the pumps used for long-term aquifer tests would
require a continuous electrical power supply, which could be
drawn from a nearby utility line.
2.8.1.1 Hydrogeologic characterization
Hydrogeologic characterization is important in defining the
ground water flow system and the extent of contamination related
to uranium processing activities at the UMTRA Ground Water Project
sites. Hydrogeologic characterization efforts would also be
essential in developing and evaluating ground water compliance
strategies.
Hydrogeologic characterization would include the following:
- A description of the hydrogeologic characteristics of the
site and surrounding land.
- A determination of aquifer hydraulic characteristics.
- The quantity of ground water and the direction of ground
water flow.
- A determination of ground water recharge and discharge areas
that may influence human health and the environment. Ground
water discharge areas would include surface water bodies and
water supply wells.
- The proximity and withdrawal rates of ground water users.
- The current and future uses of ground water in the region
surrounding the site.
Most hydrogeologic information is obtained from boreholes drilled
for the installation of monitor wells. Geophysical methods may
also be used to evaluate subsurface hydrogeologic conditions
in the vicinity of the UMTRA Project sites. Borehole information
and geophysical methods (under the appropriate conditions) can
be used to characterize hydrogeologic conditions such as depth
to bedrock, presence of sand and clay layers, and fracture zones
that may control ground water flow and contaminant migration.
Examples of some hydrogeological characterization features are
shown in Figure 2.2.
Monitor wells are used for static water level measurements,
ground water quality sampling, and aquifer testing (for example,
aquifer pumping tests or water displacement tests). Monitor
wells would be designed and installed to provide representative
ground water quality samples and aquifer test results. Ground
water flow patterns and velocities in the vicinity of the sites
would be characterized on the basis of ground water elevations
obtained from monitor wells and aquifer test data. Hydraulic
parameters that describe the way ground water moves through
the aquifer (including transmissivity, hydraulic conductivity,
and storativity) would be calculated from aquifer test data.
Figure 2.3 shows examples of a monitor
well and an extraction well.
Ground water models could be used to analyze and predict ground
water and contaminant plume movement. Models would be useful
in determining points of exposure at land surface, estimating
arrival times at specific downgradient locations or points of
exposure, and estimating contaminant concentrations at points
of compliance or points of exposure. These models would support
risk assessments and ground water compliance strategy development.
Ground water models could also be used in remediation activities.
For example, models could be used to assess ground water compliance
strategies, compare long-term effects of ground water remediation
designs, and optimize performance of aquifer remediation systems.
Figure 2.2
Hypothetical Cross Section Of Aquifer Matrix, Perched Ground
Water,
And Regional Ground Water
Figure 2.3
Schematic Diagram Of A Monitor Well And An Extraction Well
Site-specific environmental impact statements, environmental
assessments, and remedial action plans for the Surface Project
have previously described existing and potential future water
uses in the vicinity of the processing sites. As the UMTRA Ground
Water Project progresses, water uses and alternative supplies
would be monitored and addressed as needed.
2.8.1.2 Geochemical characterization
Geochemical characterization is important in defining ground
water contaminants related to uranium processing activities
and in determining contaminant interactions with the aquifer
matrix. Geochemical characterization efforts are essential to
developing ground water compliance strategies because the geochemical
composition of the aquifer matrix affects the quality of ground
water and the rate of contaminant migration.
The scope of geochemical characterization would include the
following:
- A review of the historical record of chemicals used in the
milling operation.
- A determination of the source of contamination and its cumulative
impact on the ground water quality.
- A determination of the contaminated and uncontaminated ground
water quality.
- A determination of the geochemistry of the sediment or rock
that contains the ground water (known as the aquifer matrix
material).
Ground water quality
Existing ground water characterization data would be used to
determine the need, if any, to collect additional data for ground
water characterization and risk assessments. In some cases,
additional background and downgradient ground water quality
characterization data would be collected to reduce uncertainties
in the conceptual risk model.
Background ground water quality is the water quality in an
aquifer that would be expected at a site if contamination from
the uranium processing had not occurred. Background ground water
quality is determined from hydrologically upgradient locations
or adjacent areas that have not been affected by uranium processing
activities. Some UMTRA Project sites have naturally poor background
ground water due to their proximity to uranium ore bodies. An
assessment of background ground water quality would provide
a comparison for determining the magnitude and extent of ground
water contamination caused by processing. At processing sites
with surface water in the area, background surface water quality
would also be defined upstream. See Appendix B for an expanded
discussion regarding the determination of background water quality.
The distribution of hazardous constituents in the unsaturated
zone, ground water, and surface water would be defined on the
site and downgradient from the processing sites. Figure
2.4 shows an example of a ground water contaminant plume
moving downgradient from a processing site. This information
would be used to predict contaminant migration for each site,
assess risk, and select ground water compliance strategies.
Geochemistry of aquifer matrix material
Through the geochemical processes of dissolution, precipitation,
adsorption, desorption, and ion exchange, geochemical interactions
between the ground water contamination and the aquifer matrix
influence the rate at which chemical elements and compounds
migrate through the aquifer (Table 2.1).
Therefore, geochemical characterization of the aquifer matrix
would allow for more accurate predictions of contaminant migration
velocities. Contaminant migration velocity estimates would be
critical for selecting natural flushing versus active ground
water remediation and for assessing active remediation designs.
Therefore, a detailed knowledge of the aquifer matrix chemistry
would play an important role in ground water compliance.
Geochemical characterization methods
Water quality would be assessed by collecting and analyzing
water samples from ground water monitor wells, springs, seeps,
and surface water bodies. Some basic ground water quality characteristics
could be determined in the field. Concentrations of major and
minor chemical components in the ground water would be determined
in the laboratory. Ground water quality would be evaluated using
statistical procedures such as those recommended by EPA (EPA,
1989).
The geochemistry of the aquifer matrix material is characterized
to determine mechanisms and the nature of ground water constituent
interactions with aquifer matrix material. These data could
be used in geochemical models to predict interactions and changes
in contaminated ground water as it moves downgradient. Where
the ground water compliance strategy depended on the aquifer
matrix geochemistry, geochemical modeling could be used in conjunction
with ground water flow and contaminant transport models to assess
contaminant mobility in the ground water and to predict reactions
with minerals in the unsaturated and saturated zones.
2.8.2 Ground water remediation methods
Two ground water compliance strategies are described in this
section: natural flushing and active ground water remediation.
Natural flushing is passive because it does not involve manipulation
of ground water flow, quantity, or quality. Natural flushing
means letting the natural ground water processes reduce the
contamination in ground water. This process is commonly referred
to as natural attenuation and often involves some or all of
the geochemical processes identified in Table
2.1. To effectively meet EPA standards, natural flushing
must reduce contamination to background levels, to maximum concentration
limits, or to alternate concentration limits within 100 years.
Active remediation methods involve the engineered manipulation
of ground water flow, quantity, or quality to achieve ground
water quality standards in a specified period of time. Active
remediation methods could be used in combination with natural
flushing to minimize remediation costs and to expedite remediation.
Figure 2.4
Hypothetical Cross Section Of Ground Water Contamination Plume
Table 2.1 Geochemical processes
that control contaminant migration through an aquifer
Process
|
Definition
|
| Dissolution |
|
| Precipitation |
|
| Adsorption |
|
| Desorption |
|
| Ion exchange |
|
| Biological |
|
Natural flushing
Natural flushing allows the natural ground water movement and
geochemical processes (Table 2.1) to
decrease contaminant concentrations. EPA ground water standards
require that natural flushing must reduce contamination to levels
within regulatory limits within 100 years. To select natural
flushing at a specified UMTRA Project ground water site, investigations
described in Section 2.8.1 would take place
to demonstrate its potential effectiveness at achieving EPA
ground water standards in 100 years (Figure
2.5). Under Subpart B of the EPA ground water standards,
natural flushing may be used if compliance with the standards
would occur within a period of 100 years or less; if adequate
monitoring and institutional controls were established and maintained
throughout the flushing period; if institutional controls resulted
in conditions that were protective of human health and the environment;
and if the ground water were not currently nor projected to
be a drinking water source.
Figure 2.5
Hypothetical Cross Section View Of Natural Fulshing
Active ground water remediation methods
Active ground water remediation includes several methods that
could be used in the Ground Water Project. These methods are
described in detail in Appendix C and are summarized below.
Gradient manipulation-Gradient manipulation uses either
wells or trenches to add water to an aquifer to increase ground
water velocity in a specific direction. Gradient manipulation
could be used to accelerate the process of natural flushing.
Conversely, gradient manipulation could be used to temporarily
prevent discharge of a contaminant plume into surface water
bodies by creating a hydraulic diversion to contaminated ground
water flow. Gradient manipulation could be used in conjunction
with natural flushing to decrease concentrations over a unit
area at a faster rate and to temporarily prevent the migration
of contaminants into areas where ground water was not previously
contaminated or where institutional controls cannot be effectively
applied.
Contaminant isolation-Ground water contamination sources
are the tailings and associated highly contaminated water or
adsorbed hazardous constituents in the unsaturated zone above
the water table. Zones of highly contaminated ground water below
a processing site are the result of the contamination source.
Ground water contamination sources could be mitigated or eliminated
through engineered measures to control or contain their hazardous
constituents.
Hydrologic, geochemical, and reactive barriers could be used
to keep a contaminant source from entering the ground water.
These technologies could prevent hazardous constituents from
migrating into the ground water. In areas of highly contaminated
ground water under a former tailings pile, a barrier could be
used for more efficient ground water extraction (Figure
2.6). Because of the expense involved, these techniques
would be limited to small areas of highly contaminated material
or ground water.
Ground water extraction-Ground water extraction controls
movement of contaminated ground water and removes it from the
aquifer. In many cases, it would be necessary to extract ground
water only from the most highly contaminated zones (Figure
2.7). Ground water flow information and ground water hydraulic
parameters would be used in conjunction with optimization codes
to design the extraction network including well numbers, depths,
spacing, and pumping or injection rates. With the aid of ground
water models, the time required for the remedial actions could
be estimated.
Well systems could be used to extract contaminated ground water
for treatment or to create hydraulic barriers to ground water
flow and increase the efficiency of extraction. These wells
would then be pumped at specified rates to control the movement
of contaminated ground water. In some cases, it could be necessary
to combine periods of well pumping with periods of no pumping.
When pumping has stopped, contaminants can diffuse out of less
permeable (fine grain) zones or desorb from the aquifer matrix
until equilibrium concentrations are reestablished in the ground
water. Subsequent pumping would remove the minimum volume of
contaminated ground water at the maximum possible concentration.
Figure 2.6
Low-Permeability To Enhance Ground Water Extraction
Figure 2.7
Hypothetical View Of Ground Water Extraction
In shallow ground water systems, a well point network consisting
of closely spaced, shallow wells connected to a pipe with a
centrally located suction lift pump could be used. These systems
can create an effective hydraulic barrier by capturing contaminated
ground water. Well point networks would be used mainly for shallow
water table aquifers because the maximum drawdown obtainable
by suction lift is limited to approximately 25 feet (ft) (8
meters [m]) at sea level. Because well points are smaller in
diameter and shallower than monitor wells, they are simpler
and cheaper to install. This method is temporary (i.e., when
the pumping is stopped the barrier ceases to function).
The land application option of ground water disposal would
use extracted ground water for agricultural irrigation. Extracted
ground water would undergo treatment before use as irrigation
water when necessary. This option would be used at processing
sites located close to agricultural lands. Processing sites
with ground water contaminant plumes containing nitrates would
be the most likely candidates for this type of water disposal
design.
Contaminated ground water treatment-Once contaminated
ground water is extracted from an aquifer, it may be necessary
to treat it to protect human health and the environment. The
need for treating extracted contaminated ground water before
it is discharged depends on the concentrations of contaminants
in the extracted ground water and the regulations regarding
discharge of effluent to the surface and ground water. Once
treated, ground water could be discharged to surface water bodies,
recharged back into a shallow aquifer, or used as irrigation
water for agricultural purposes.
Contaminants in water and wastewater could be removed by physical,
chemical, and biological methods. These methods are discussed
in detail in Appendix C.
In situ ground water treatment-In situ
(in place) treatment uses chemical agents in the affected soil
or ground water to degrade, remove, or immobilize the contaminants.
It also includes methods for delivering solutions to the subsurface
and for controlling the spread of contaminants and chemical
agents beyond the treatment zone.
In situ treatment processes are generally divided into
three categories: biological, chemical, and physical. In
situ bioremediation accelerates or enhances the rate of
microbial reactions to transform the contaminants into benign
or insoluble compounds. At UMTRA Project sites, in situ
treatment could be used to reduce nitrates through denitrification
or to remove metals using sulfate. With chemical in situ treatment,
specific chemicals are injected into the soil or ground water
to degrade, immobilize, or release contaminants that are in
the ground water or attached to the soil particles. Physical
in situ methods physically change the soil or ground
water using heat, electric energy, or other means to immobilize
or to expedite the release or movement of contaminants from
the soil or water. In most instances, in situ treatment
would be combined with aboveground treatment to achieve the
most cost-effective treatment at the UMTRA Project sites.
In some cases, geochemical barriers may be effective in eliminating
or reducing ground water contamination. A subsurface permeable
barrier would be placed to intercept the flow of contaminated
ground water for shallow ground water systems. As the ground
water passes through the barrier, the contaminants interact
with the barrier material and are removed from the ground water
by precipitation or adsorption.
2.9 WASTE MANAGEMENT METHODS
Various types of wastes may be generated during ground water
characterization, monitoring, and remediation. The UMTRA Project
would follow the Technical Approach for the Management of
UMTRA Ground Water Investigation-Derived Wastes to manage
field-generated wastes from well drilling, well development,
sampling, testing, ground water monitoring, and remediation
(DOE, 1994c). This report also provides details on the regulatory
requirements for managing and disposing of ground water investigation-derived
wastes. The information below summarizes this report (DOE, 1994c).
When a ground water compliance strategy is determined and has
the potential to form waste material, the management and regulation
of this waste would be analyzed in the site-specific environmental
document.
The proposed action, the active remediation to background alternative,
and the passive remediation alternative have the potential of
generating the following materials that may be contaminated:
- Well development water-Well development water is generated
when new wells are drilled for site characterization, installation
of a monitoring system, and active remediation field operations.
If necessary, well development water would be treated, and
either reinjected into the ground water, applied to the land,
or transported to an open UMTRA Project cell or other licensed
facility for disposal in a manner consistent with UMTRA Project
standards and/or DOE orders.
- Drill cuttings and drilling muds-Drill cuttings and drilling
muds are the soil and rock brought to surface by the drill
when drilling a well. These materials are generated during
site characterization, installation of a monitoring system,
and drilling during active remediation. Drill cuttings and
drilling muds would be analyzed and either applied to the
land or transported to an open UMTRA Project cell or other
licensed facility for disposal in a manner consistent with
UMTRA Project standards and/or DOE orders.
- Purge water-Purge water is generated prior to ground water
sampling. Ground water sampling from wells would occur during
site characterization and monitoring. Purge water would be
analyzed and either be evaporated, applied to the land, or
discharged in a manner consistent with UMTRA Project standards
and/or DOE orders.
- Sludge and brine-Sludge and brine result from the treatment
of contaminated ground water. Sludge and brine could be generated
during site characterization or active remediation field operations.
Sludge and brine would be analyzed and disposed of at an open
UMTRA Project cell or at an alternate disposal site in a manner
consistent with UMTRA Project standards and/or DOE orders.
- Ground water and soils-Contaminated ground water and soils
may be generated during active remediation field operations.
If necessary, contaminated ground water would be analyzed
and treated. Ground water would then either be reinjected
into the ground water, applied to the land, or discharged
to a surface water body in a manner consistent with UMTRA
Project standards and/or DOE orders. Soils would either be
applied to the land or transported to an open UMTRA Project
cell for disposal in a manner consistent with UMTRA Project
standards and/or DOE orders.
Prior to disposal in an UMTRA Project disposal cell, wastes
would be evaluated to ensure they would not compromise the cell
design. If the quantity of liquid wastes exceeds the design
parameters of a disposal cell, the liquid waste quantity would
be reduced. Waste that could not be accommodated in an UMTRA
Project disposal cell would be disposed of at a licensed disposal
facility.
All these materials would have the potential of being contaminated
with constituents typical of uranium mill processing and being
considered residual radioactive materials. These materials would
be managed in accordance with the requirements of the UMTRCA,
the DOE, EPA, and the appropriate Indian tribes and states.
Current data from most sites do not suggest contaminated materials
from sources other than uranium processing activities would
be encountered, although at some sites naturally occurring ore
bodies may be encountered. However, all contaminants from non-UMTRA
sources, if encountered, would be managed in accordance with
the appropriate requirements.
2.10 COST ESTIMATE METHODS
Since a budget must be developed to obtain yearly federal appropriations,
assumptions concerning site-specific compliance strategies must
be made in advance to derive a cost estimate that will support
budget submittals. These assumptions are for budgetary reasons
only and in no way indicate that site-specific ground water
compliance strategy decisions have been made prior to completion
of the PEIS or a site-specific environmental document.
In estimating costs for each of the three strategies (no remediation,
natural flushing, and active remediation), certain generic activities
are assumed to support all three proposed strategies. However,
the duration, complexity, and cost range of these generic activities
vary with the type of compliance strategy selected. These activities
include 1) preparing baseline risk assessments, site observational
work plans (considered part of detailed site characterization),
environmental assessments, and remedial action plans or modifications;
2) conducting a limited monitoring program until implementation
of a compliance strategy or closeout activity; 3) performing
some type of closeout activity, such as a certification report,
a modification to the long-term surveillance plan, and/or licensing;
and 4) performing program support activities. The cost estimates
include escalation and contingency.
Activities for the no remediation compliance strategy would
include those listed above plus, in certain cases, additional
site characterization, wells, and revisions to the site observational
work plans. Activities for the natural flushing compliance strategy
would include longer durations of the same activities plus various
phases of monitoring (calibration monitoring and verification
monitoring) and a longer period to close out the site following
verification monitoring and prior to turning the site over to
another DOE project for compliance monitoring. Natural flushing
also would include institutional controls. In addition to the
above, active compliance strategy sites require detailed construction
estimates. In developing these estimates, the Project used a
software package called the "G-2 Estimator" in conjunction
with environmental construction databases based on UMTRA Surface
Project experience. All major cost elements were priced separately
using historical data and supplier quotes. Cost elements included
utility installation, numbers of wells required, collection
systems, installation of water treatment plants, plant operations,
testing, land application of treated or untreated water, closure,
demobilization, and site restoration. The plant size and length
of operations were generated on a site-specific basis using
current assumptions on technical parameters of the plume, soil,
and contaminants.
Each activity was individually reviewed. Cost estimates were
developed based on related historical actuals (approximately
10 years on the UMTRA Surface Project), similar experience on
other projects, and/or best professional estimates. The activities
were then tailored to each site based on such site-specific
attributes as the estimated volume of the plume and contaminants
present. A critical path method analysis was then used to develop
sequential logic for each compliance strategy, since some activities
occur concurrently while others are sequential, and then summarized
to develop an overall schedule. The overall Project schedule
supported development of non-site-specific Project support activities,
processes, or deliverables. The non-site-specific cost estimates
were allocated against activities each year and combined to
develop a total Project cost.
The last step in developing the cost estimates was to apply
contingency to the base estimates to cover uncertainties. Acceptance
of the proposed strategies used for the federal budgeting exercise
accounts for the largest share of the Project's identified contingency.
Other uncertainties to the UMTRA Project's estimates include
1) delays in state-share funding; 2) perturbations and delays
in federal funding; 3) lack of access to existing site wells
or the inability to drill new wells due to lack of access; 4)
changes in currently understood plume size and contaminant concentrations;
and 5) unknowns. The basis of estimates has attempted to cover
a portion of the above risks; however, each time a project estimate
is made, the DOE reexamines contingency application.
The basis of estimates for costs is reviewed several times
during the fiscal year beginning in January. The estimates are
continually reviewed for reasonableness, adaptability to the
technical and political environment, and sound estimating practices.
|