Modification 038 to the Fernald Closure Contract
(DE-AC24-01OH20115) was signed on March 29, 2003.
Modification 038 clarified the scope of work and definition of
closure; brought scope into the contract; eliminated the
“completion” definition; and incentivized achievement of the
December 31, 2006, target closure date. The significance of
the Modification 038 provisions necessitated that both the
Performance Management Baseline (PMB) and the Performance
Management Plan (PMP) be updated. The Modification 038
Baseline Replan that updated the PMB was approved by EM-1 on
October 1, 2003. The PMP update was approved by the EM
Configuration Control Board on December 18, 2003.
|