Soil and Disposal Facility Project


8194-2

 
Work Scope  

bullet item

 

Remediate and dispose of contaminated soil
bullet item Certify site as "clean" and perform substantial natural resource restoration

Cleanup Remedy

bullet item Records of Decision signed in 1995 and 1996
bullet item Excavate approximately 2.5 million cubic yards of soil, foundations and below-grade piping
bullet item Certify that remaining soil meets EPA-established cleanup levels
bullet item Design, construct and operate an On-Site Disposal Facility with capacity to hold 2.94 million cubic yards of contaminated soil and debris

Status (as of 7/06)

bullet item

Project - 100 percent complete

bullet item

Designed, built and closed the On-site Disposal Facility

bullet item

Excavated and dispositioned over 2.95 million cubic yards of contaminated soil and debris

Project Completion - 2006

For More Information
For specific questions about this project contact Sue Walpole, S. M. Stoller, at 513-648-4026, e-mail: Sue.Walpole@lm.doe.gov. 

Aquifer | Cleanup | Cleanup Highlights | D&D | Environmental Monitoring | Nuclear Material | Silos 1-2  | Silo 3 | SDFP | Waste Management | WPRAP 

Navigation Bar

Together, DOE and Fluor Fernald were committed to safely restoring the 
Fernald site to an end state that serves the needs of the community.